Team shows effectiveness of small-footprint groundwater remediation technology  

Higher than 95%

contaminant degradation

10 times

rate of impacted water flow in our previous test

Approx. 35%

cost savings vs. conventional pump-and-treat approach

Summary

  • The U.S. Department of Defense (DOD) wanted to find a cheaper, more efficient solution for remediating large, deep, dilute groundwater plumes.  
  • Backed by competitive DOD funding, Haley & Aldrich honed an existing remediation approach to shrink the aboveground footprint of the installation needed to perform the work.  
  • This technology involves a new approach to achieve an effective 1,4-dioxane treatment through a belowground bioreactor and, at the same time, to reduce bioclogging. 
  • A field test at a DOD site in Arizona successfully demonstrated the feasibility of this small-footprint treatment technology for large, deep, dilute groundwater plumes that can save costs and minimize site access constraints on groundwater cleanup. 